摘要
为了实现渤海油田间的海管联网,海洋石油工程股份有限公司根据业主的要求,在渤南-龙口14”天然气外输管线上进行了不停输带压开孔作业,以便连接来自PL19-3油田的新铺管线。根据这一项目实例,阐述了水下不停输带压开孔技术和方法在海管连接方面的应用。
According to the owner' s requirement, Offshore Oil Engineering Company (COOEC) did the hot tapping operations at 14" BoNan to LongKou gas export pipeline so that it can be connected with new pipeline laid from PL19-3 oil field in BoHai bay. Refer to the project, this paper main describes the hot tapping technology which be used in the part of pipeline connection.
出处
《中国造船》
EI
CSCD
北大核心
2011年第A02期234-238,共5页
Shipbuilding of China