介绍了华电能源哈尔滨第三发电厂200 MW机组锅炉灭火保护系统优化前存在的问题,通过对系统的分析和实践,总结出优化后的解决方案并进行了实施,进一步提高了机组运行的可靠性。
The problems existing in original FSSS of the 200MW unit boiler of Huadian Energy Harbin Third Power Plant were introduced.According to analysis of the system and practice,the optimized solution was summarized and implemented;the operation reliability of the unit was enhanced further.
出处
《华电技术》
CAS
2011年第8期62-66,80,共5页
HUADIAN TECHNOLOGY
关键词
200
MW机组
灭火保护系统
优化
可编程控制系统
200MW unit
furnace safeguard supervision system(FSSS)
optimization
programmable logic control(PLC) system