摘要
对现有粪便处理厂粪便消化液处理工艺进行了分析,找出了存在的问题,并根据工程改造的原则,将沉淀池改为缺氧池和厌氧池,SBR池改为ICEAS池,采用改良A2+ICEAS组合工艺处理粪便消化液。结合工程改造情况,介绍了主要构筑物和设计参数,并对经济技术指标进行了分析,为相关工程设计提供借鉴。
The original treatment process of digested fecal sewage in a night soil treatment plant was analyzed, and problems of the process were found out. According to the principles of reconstruction project, the settling tank was transformed into anoxic and anaerobic tanks, SBR was replaced by ICEAS, and the digested fecal sewage was treated by modified A^2 + ICEAS process. The process reconstruction, main constructions and technical parameters were introduced, and the technical and economic indexes were analyzed, giving a reference to design of similar projects.