兖州煤业股份有限公司济宁三号煤矿建设一套电吸附除盐系统,对8000m3/d矿井水进行处理后供济三电厂作为循环水补充水。简介了该系统的工艺流程及工程规模。该系统运行效果良好,取得了较高的社会、经济效益。
An electrosorption demineralization system was set up in Jining No.3 coal mine of Yanzhou coal mining co.ltd.The 8000m3/d mine water is treated for the use of Jinning No.3 power plant circulating water addition.The system process and scale are introduced.The system is running well and achieved high social and economic benefits.
出处
《煤矿现代化》
2011年第3期18-19,共2页
Coal Mine Modernization
关键词
矿井水
电吸附
工程应用
mine water
electrosorption
engineer application