摘要
介绍了高速铁路高架站到发线简支箱梁利用既有梁场进行预制架设施工方案,根据现有施工设备及节点工期要求,为了加快施工进度,消除和减少对后期工程的影响,且减少项目投资的目的,对高架站到发线箱梁利用既有设备改造后进行预制架设。
The paper introduces the construction plan for prefabricated erection of high-speed railway projects from Elevated box beam to departure line simple box girder with existing beam field.Under the existing schedule node requirements and construction equipment,in order to speed up the construction schedule,eliminate and reduce the impact on later works,as well as to reduce investment,the paper also describes in detail the use of modified existing equipments for prefabricated erection.It is of good reference and research value for similar design and construction.
出处
《铁道建筑技术》
2011年第4期14-16,27,共4页
Railway Construction Technology
关键词
高速铁路
高架车站
箱梁预制
架设设备
既有梁场
high-speed railway
elevated station
prefabricated box beam
erection equipment
existing beam field