安庆铜矿在尾矿资源综合回收工作中,坚持 先试验研究,抓产品市场调研,最后 投资建厂的原则,降低了风险。同时,充分利用矿山废旧设备 和自制设备,节省了一次性投资,达到 了上马快,见效快,风险小的目的。
In its comprehensive recovery of the tailings resource,Anqing Copper Mine adhered to the principle of the experimental research and the investigation of the product market coming before the investment and the construction so as to reduce the risk.Meanwhile,the full utilization of old and disused equipment and the self manufacture of some equipment helped save one time investment.As a result,the aim of rapid commissioning,quick return and low risk were achieved.Practice of the Co m prehensive Recoveryof the Tailings Resource at Anqing Copper Mine Niu Zh
出处
《金属矿山》
CAS
北大核心
1999年第8期5-7,共3页
Metal Mine
关键词
尾矿资源
综合利用
生产实践
试验研究
铜矿
Tailings resource,Comprehensive utilization,Production practive,Experimental research