600MW机组高压加热器疏水控制系统改进 被引量:2

Improvement of Drainage Control System for High Pressure Heaters of 600 MW Units
下载PDF
导出
摘要 分析了北仑发电厂600 MW机组高加疏水控制系统存在的问题,提出了通过单室平衡容器实现疏水水位差压式测量;进行疏水水位测量压力温度修正和疏水水位控制由基地式控制改为DCS控制的改进方案,可为存在类似问题的发电厂提供参考和借鉴。 This paper analyses the existing problems of the drainage control system for high pressure heaters of 600 MW units in Beilun Power Plant and offers the improvement scheme, in which the drainage water level differential pressure measurement is achieved with a single chamber balance vessel. In addition, the pressure and temperature are corrected for drainage water level measurement and local control of drainage water level. is replaced with distributed control system (DCS). It can serve as a reference for other power plants with the similar problems.
出处 《浙江电力》 2011年第3期40-42,共3页 Zhejiang Electric Power
关键词 高压加热器 疏水 基地式控制 压力修正 端差 high pressure heater drainage local control pressure correction terminal temperature difference
  • 相关文献

参考文献2

共引文献1

同被引文献11

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部