大相岭泥巴山隧道涌水大变形处理技术 被引量:5

Treatment Techniques for Water Gushing and Large Deformations of Daxiangling Tunnel
下载PDF
导出
摘要 雅西高速公路大相岭隧道全长10 007 m,单口掘进5 130 m,为全国单口掘进之最,地质情况极为复杂,施工中出现了严重的涌水、大变形事故。为了能安全通过大相岭隧道右线41 m集涌水、大变形、断层破碎带地段,采用了分步开挖、分部引排水、初期支护全断面封闭成环、φ42小导管超前支护等施工技术以及严格控制注浆压力、短台阶开挖、加快下导洞施工进度、二次衬砌紧跟等施工工艺,保证了结构的安全稳定及工程的稳步推进。 Daxiangling tunnel is 10 007 m long with extremely bad geological conditions,of which one end excavation length reached 5 130m,the highest record in China.Serious water gushing and large deformations encountered during construction.In order to safely pass through the 41m section with gushing water,large deformations and fault fractures on Daxiangling tunnel right line,treatment measures were adopted,including excavation and drainage by parts,full face closure of primary support,advanceφ42 pipe roofing,strict control of grouting pressures,excavation with short benches,secondary lining cast in time,etc.Project safety and stability were ensured.
作者 王晋生
出处 《现代隧道技术》 EI 北大核心 2010年第6期91-94,共4页 Modern Tunnelling Technology
关键词 公路隧道 涌水 大变形 断层 处理技术 Highway Tunnel Water gushing Large deformation Fault Treatment technology
  • 相关文献

参考文献8

二级参考文献6

共引文献57

同被引文献40

引证文献5

二级引证文献25

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部