时速350km高速铁路大跨度连续梁悬浇施工监控 被引量:5

Construction Monitoring and Control of Cantilever Casting of Long Span Continuous Girder for 350 km/h High-Speed Railway
下载PDF
导出
摘要 津秦客运专线设计为时速350 km的高速铁路,该铁路线上的下邬蓟运河特大桥上跨唐津高速公路,为(80.6+128+80.6)m三向预应力混凝土连续箱梁桥,采用挂篮悬浇施工。采用桥梁博士3.0建立有限元计算模型,计算梁体线形和应力。施工中对梁体线形和应力进行实时监测,并将实测结果与计算结果进行对比。结果表明:该桥施工监控保证了连续梁施工中结构处于稳定状态,最终线形控制结果较为理想。 The Tianjin-Qinhuangdao Passenger Dedicated Railway is designed as a high-speed railway of 350 km/h.The Xiawuji Canal Bridge on the railway spanning the Tangshan-Tianjin Expressway is a three-way prestressed concrete continuous box girder bridge with span arrangement(80.6+128+80.6) m and the girder of the bridge is constructed by the cantilever casting by form travelers.The software of Bridge Doctor 3.0 is used to set up the finite element calculation models,the geometric shape and stress of the girder are calculated and are monitored in real time in the construction process and the filed measurements of the girder are compared to the calculations.The results show that the construction monitoring and control of the girder have ensured the stability status of the girder in the construction and the final controlled geometric shape of the girder is satisfactory.
作者 沈金贵
出处 《世界桥梁》 北大核心 2011年第1期35-37,共3页 World Bridges
关键词 客运专线 连续梁桥 挂篮悬浇施工 线形 应力 施工监控 passenger dedicated railway continuous girder bridge cantilever casting construction by form traveler geometric shape stress construction monitoring and control
  • 相关文献

参考文献5

  • 1吴向军.下坞蓟运河特大桥跨津山铁路施工方案设计[J].世界桥梁,2010,38(2):9-12. 被引量:2
  • 2TB10002.3-2005,铁路桥涵混凝土和预应力混凝土结构设计规范[s]. 被引量:1
  • 3张继尧,王昌将编著..悬臂浇筑预应力混凝土连续梁桥[M].北京:人民交通出版社,2004:283.
  • 4TZ213-2005,客运专线铁路桥涵工程施工技术指南[S]. 被引量:115
  • 5鲍卫刚编著..预应力混凝土梁式桥梁设计施工技术指南[M].北京:人民交通出版社,2009:343.

共引文献115

同被引文献29

引证文献5

二级引证文献25

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部