季节性冻土地区客运专线路基基床结构优化 被引量:3

Subgrade Bed Structural Improvement of High Speed Railway in Seasonal Frozen Region
下载PDF
导出
摘要 对季节性冻土地区客运专线的路基基床结构进行了优化,通过现场填筑试验证实优化后的路基基床填筑方案,即铺设两布一膜,上覆5 cm中粗砂,再铺设55 cm厚级配碎石达到了检验标准,可在所研究的工程中推广使用。同时提出采用C25纤维混凝土代替原设计8 cm沥青混凝土作为防水层,优化后的防水层在施工操作性和质量保证方面有较大优势。 This paper makes the subgrade bed structural improvement of High Speed Railway in seasonal frozen region.The optimized option of subgrade bed structure is layed geotextile firstly,placed 5 cm thickness sand secondly,and 55 cm thickness graded crushed stone lastly,the option is proved to conform to standard.Therefore,the optimized option of subgrade bed structure is used on the engineering construction.The bituminous concrete is replaced by C25 fiber-reinforced concrete to be as the material of 8 cm waterproof layer.The latter has the advantages of easy operation and quality assurance.
作者 王珣 时伟
出处 《中国港湾建设》 北大核心 2010年第6期37-38,共2页 China Harbour Engineering
关键词 级配碎石 防水层 路基基床 季节性冻土 客运专线 graded crushed stone waterproof layer subgrade bed seasonal frozen region High Speed Railway
  • 相关文献

参考文献2

二级参考文献7

共引文献7

同被引文献40

引证文献3

二级引证文献85

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部