摘要 本文为解决设备安装序列规划中广泛存在的综合决策问题,提出改良的模糊层次综合评价法,并应用该方法对磨煤机安装序列规划的实际案例进行综合评判决策,给出计算过程,得出最终综合评价的具体分数。模糊层次综合评价法较好的解决了矩阵难以满足一致性、专家难以确定指标属性值等问题,较好地实现对磨煤机安装序列的综合评价,对实际工作中最佳装配方案的选择提供了有效指导。 In order to address the widespread issue of integrated decision-making of installation project, an improved fuzzy hierarchy comprehensive evaluation method is proposed in this paper. Besides, the method is applied to evaluate an actual case of pulverizer installation sequence planning. The calculating procedure and the final points of comprehensive evaluation are also provided. Fuzzy hierarchy comprehensive evaluation method could solve the problems that it is difficult to achieve the consistency of matrix and to determine the property value. Otherwise, this method could conduce to obtain a better comprehensive evaluation sequence of the pulverizer installation and choose the best optimizing assembly program in actual construction project.
出处 《东北电力大学学报》 2010年第1期10-14,共5页 Journal of Northeast Electric Power University
基金 国家自然科学基金项目(50606005)
关键词 电厂设备 安装序列 模糊综合评价 层次分析法 power plant equipment installation sequence fuzzy comprehensive evaluation AHP
  • 相关文献

参考文献10

二级参考文献35

  • 1邹开其.模糊系统与专家系统[M].成都:西南交通大学出版社,1991.90-102. 被引量:4
  • 2帕尔G,拜茨W 冯培恩(译).工程设计学[M].北京:机械工业出版社,1992.. 被引量:3
  • 3SUH N P. The principles of design[M]. London: Oxford Univ. Press, 1990. 被引量:1
  • 4PAHI G, BEITZ W. Engineering design-a systematic approach[M]. London: The Design Council, 1988. 被引量:1
  • 5Ulf Slrom & Alan Axworthy. Product Configurators-The Big Picture. JULY 2000 MIDRANGE ERP. 被引量:1
  • 6Daniel Sabin & Rainer Weigel. Product Configuration Frameworks- A Survey. IEEE INTELLIGENT SYSTMS, JULY/AUGUST 1998. 被引量:1
  • 7Gfirel Hedin, Lennart Ohisson, and John McKenna. Product Configuration Using Object Oriented Grammars. In Proceedings of the 8th International Symposium on System Configuration Management (SCM - 8), Brussels, July 20 - 21, 1998.LNCS- 1439, pp 107 - 126, Springer- Verlag. 被引量:1
  • 8Ping Yi Chao, Tsung Te Chen. Analysis of assembly through product configuration. Computers in Industry 44 (2001) 189-203. 被引量:1
  • 9Relaecca Duray, Peter T Ward, Glenn W MiUigan, William L Berry. Approaches to mass customization: eonfigurations and empirical validation. Journal of Operafiom Management,2000. 18:605-625. 被引量:1
  • 10Huiping Shen, Kwun - Lon Ting, Tingli Yang. Configuration analysis of complex muhiloop linkages and manipulators.Mechanism and Machine Theory, 2000. 35:353-362. 被引量:1

共引文献76

同被引文献47

引证文献6

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部