摘要
运用了生产线平衡的理论知识,对生产T5B牙刷的Z11植磨毛生产线进行了优化。首先,对该生产线的现状进行了详细的调查,通过秒表测时法对各生产单元的时间进行了测定。然后,运用IE方法和生产线平衡的原则以及速度图,找出了瓶颈单元,根据ECRS原则进行了两次改善。最后,分别计算了改善前和改善后的生产线平衡率,对改善的效果进行了比较,达到了平衡劳动负荷、提高效率的目的。
It describes the optimization of the Zll T/F grinding tiloplume production hne based on the meory of production line balance and lean production. It analyzes the data and information exactly from the production line, measures the time of working procedures. Using IE methods of lean production and the principle of production line balance, it studies the bottleneck element, proposes the way to reduce the working time with the ECRS methods. It calculates the line efficiency and compares the results before and after improved. This method can enhance the productivity and balance the workload.
基金
南京农业大学工学院引进人才启动基金资助项目(RCQD07-01)
南京农业大学青年科技创新基金资助项目(KJ09031)
关键词
IE方法
生产线平衡
劳动负荷
IE Technique
Lean Production
Line Balance
Workload