结合工作实践,介绍了空心板梁安装要点,同时阐述了后连续施工工艺,并对桥面铺装、伸缩缝施工、人行道板及栏杆等施工方案进行了描述,以积累相关施工经验,确保施工质量。
By combining with working practice,the paper introduces the points for the installation of the hollow slab beam,illustrates the continuous construction craft,and describes the construction scheme,including bridge deck pavement,expansion joint construction,foot-slab and rail,so as to accumulate construction experience and ensure the construction quality.
出处
《山西建筑》
2010年第12期144-145,共2页
Shanxi Architecture
关键词
空心板梁安装
后连续施工
伸缩缝
人行道板
installation of hollow slab beam
continuous construction
expansion joint
foot-slab