摘要 急倾斜煤层开采形成的采空区水患问题是主要灾害之一。地下水系统中的渗流具有非线性特征。随采深增加,渗水半径与渗流量加大,给安全生产带来威胁。以铁厂沟煤矿+645水平45#煤层掘进工作面探放水为例,通过现场开采情况调查,采用矿用坑道钻机进行探查预计,确保矿井安全掘进及生产,为开采扰动范围灾变预报和控制提供了借鉴。 The historical mining for steep coal seam had formed many mined-out-area in Wulumuqi coal region. The problem of flooding was one of the major sources of disaster. With the increasing of mining depth, water seepage radius increased, the amount of water seepage also increased, which even brought to risk for the safe production. Taking the working face of + 645 m of No. 45 seam at Tiechanggou coal mine as an example, the prediction and drainage were applied to the tunneling. Based on field surveys and co ensure mprehensive analysis of the exploitation, the tunnel drilling rigs for exploration were applied to the safe tunneling and production. This provides a reference for prediction and control in the disturbed zone.
出处 《西安科技大学学报》 CAS 北大核心 2010年第2期136-140,共5页 Journal of Xi’an University of Science and Technology
基金 国家自然科学基金项目(10772144) 教育部博士点基金项目(200961211100001) 陕西省重点实验室资助项目(09JS018)
关键词 急倾斜煤层 采空区渗流 灾变行为 水患防治 heavy steep and thick seam seepage of mined out area disaster behavior seepage prevention
  • 相关文献

参考文献8

二级参考文献15

共引文献90

同被引文献33

引证文献6

二级引证文献35

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部