摘要 结合新建单线电气化铁路工程昆河线玉溪至蒙自段旧寨隧道出口地热段的施工,介绍隧道地热高温段所采用的综合施工降温技术:采用帷幕注浆堵水、加强通风、冰块冷却降温、保温管排水、低温室等综合配套降温技术,将长900 m、最高温度达52℃的高地热影响段施工温度降低至32℃以下,确保隧道安全顺利施工。 Combined with the ground heat section construction in Jiuzhai Tunnel exit of Yuxi-Mengzi Section of the new single-line electrified railway project Kunhe Line,this paper gives details in comprehensive construction cooling techniques for high temperatured section in the tunnel,including water-stop by curtain grouting,enhancing ventilation,ice cube cooling,insulating pipe draining,low temperatured room and other complicated assisting techniques,so as to reduce construction temperature of the 900 m section which is highly affected by ground heat from 52 ℃ maximum to below 32 ℃,which does great benefits to the safe completion of the tunnel.
作者 刘坚
出处 《铁道建筑技术》 2010年第2期19-22,39,共5页 Railway Construction Technology
关键词 铁路隧道 高温地热水 降温技术 railway tunnel high-temperatured ground heat water cooling technique
  • 相关文献

参考文献2

二级参考文献3

  • 1张国云.隧道及地下工程岩爆与地热问题调研报告[R].北京:铁道部隧道工程局科研所,2000.. 被引量:1
  • 2铁道第一勘察设计院.青藏铁路格拉段羊八井隧道勘测资料[R].兰州:铁道第一勘察设计院,2001.. 被引量:1
  • 3康文华.西藏羊八井地热地质[J].中国科学院地质力学研究所所刊,1985,6. 被引量:1

共引文献18

同被引文献59

引证文献13

二级引证文献73

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部