摘要
结合槟城二桥主桥区域地质情况,介绍了利用起始平台和已沉放完成的钢护筒作支撑的移动式悬臂导向架进行钢护筒沉放施工的设计方案和设备配置,并具体阐述了钢护筒施工方法,对施工过程中的注意事项和质量控制方法进行了总结。
By combining with the geological situation of the main bridge region of Bineheng Second Bridge, the paper introduces the design scheme and equipment allocation of the steel casing settlement construction of the mobile cantilever guidance frame supported by the initial plat- form and settled steel casing, illustrates the construction method for the steel casing, and sums up the precautions and quality controlling methods in the construction process.