摘要
通过对国华徐州电厂现有锅炉补给水处理系统的产水量标定、产水水质测定、设备状态评估以及经济性评价,全面论证了将它用于现有2×220MW机组和新建2×1000MW机组的可行性,并提出了设备改造和系统优化方案。
Through the analysis of the water production demarcation, water quality determination, equipment status evaluation and economic estimation of the feedwater treatment system of the boiler currently used in Guohua Xuzhou power generation Co., Ltd., the feasibility of using the said system in 2 × 220 MW thermal power units and new-built 2 × 1 000 MW units was demonstrated, and the schemes for equipment reconstruction and system optimization were also put forward.
出处
《工业用水与废水》
CAS
2010年第1期22-24,共3页
Industrial Water & Wastewater
关键词
锅炉补给水处理
超超临界机组
系统优化
经济性分析
可行性研究
boiler feedwater treatment
uhra-supercritical units
system optimization
economic estimation
feasibility study