杨坞口隧道塌方综合处理措施 被引量:1

下载PDF
导出
摘要 杨坞口隧道位于杭新景高速公路千岛湖支线古滑坡段,受围岩破碎和雨季渗水影响,施工中出现了右洞塌方。经采用动态设计法,应用喷射混凝土封闭地表雨水下渗通道,地表注浆加固地层等措施进行塌方治理和山体加固;采取超前小导管和环向小导管注浆加固围岩,强化临时支护,及时封闭衬砌等措施,并采取双侧壁导坑法进行隧道施工,取得了良好效果。现场监测数据表明该治理方案合理且行之有效,治理措施可供相关工程借鉴和参考。
出处 《公路隧道》 2010年第1期33-36,共4页 Highway Tunnel
  • 相关文献

参考文献4

二级参考文献7

  • 1Bobet, A., Effect of pore water pressure on tunnel support during static and seismic loading [J]. Tunneling and Underground Space Technology, 2003,(18):377-393. 被引量:1
  • 2Lee, I.M. and Nam, S.W., The study of seepage forces acting on the tunnel lining and tunnel face in shallow tunnels, Tunneling and Underground Space Technology [J], 2001, (16):31-40. 被引量:1
  • 3Chen,W. and Ruan,H.N., Modeling coupled hydro-mechanical response of heterogeneous fractured rock during tunnel excavation [C].Proceedings of 4th Asian rock mechanics symposium, World Scientific Publishing Co. Pte. Ltd, 2006. 被引量:1
  • 4Lewis, R. W. and Schrefler, B. A., The finite element method in the deformation and consolidation of porous media. Wiley, New York,1987. 被引量:1
  • 5Dagger, M.S., A fully coupled two-phase flow and rock deformation model for reservoir rock. PhD. dissertation, University of Oklahoma, Graduate College. 2000. 被引量:1
  • 6ABAQUS Manuals-version 6.6, Pawtucket, Rhode Island, USA: Hibbitt, Karlson and Sorensen Inc.2005. 被引量:1
  • 7张涛,夏述光,谭显坤,周小飞,王元汉.断裂构造对山区公路隧道选线与施工的影响研究[J].岩土力学,2005,26(S2):275-278. 被引量:8

共引文献57

同被引文献40

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部