以武广客运专线为例,阐述在客运专线双块式无砟轨道Ⅱ线道床板施工中,如何利用Ⅰ线组织物流运输;重点对设备配置作了说明,并对几种方案进行了对比分析,可为类似工程提供参考。
Taking Wuguang passenger dedicated line as an example, the article describes logistic transportation schemes with Line I in slab construction of Line Ⅱ of double-block type non-ballast track for passenger dedicated line, and mainly explains the equipment allocation, analyzes and compares several schemes so that some references can be used by the similar works.
出处
《铁道建筑》
北大核心
2010年第1期35-38,共4页
Railway Engineering
关键词
客运专线
双块式无砟轨道
Ⅱ线施工
物流组织
passenger dedicated line
double-block non-ballast track
logistic organization