期刊文献+

某电厂1号炉包墙过热器频繁爆管试验分析 被引量:4

TEST AND ANALYSIS OF FREQUENT TUBE-BURST ON THE STEAM-COOLED WALL OF BOILER NO.1 IN ONE POWER PLANT
下载PDF
导出
摘要 某电厂1号锅炉包墙过热器运行10年来共发生爆管、泄漏30余次,利用化学成分分析、金相组织分析,以及扫描电镜、俄歇能谱等方法对其进行了分析。结果表明,包墙管材质12Cr1MoV中有害元素(As、Sn)含量过高使该管材产生回火脆性,加之焊接工艺不当促进了这种脆性程度,是造成频繁爆管的主要原因。为此,建议对包墙过热器管材进行更换。 Tube - burst and leakage on the steam - cooled wall of boiler no. 1 in one power plant had occurred more than thirty times in ten years of operation. By using chemical analysis, metallurgical structure analysis, as well as scanning electron microscope, and auger spectrometer etc. , the tubeburst and leakage have been analysed. Resrlts show that the harmful elements content of As + Sn being too high in pipe material of said steam- cooled wall made the pipe material to produce temper brittleness, and unsuitable weld procedure made the said brittleness to be more serious, were the main causes leading to tube - burst and leakage. For this,it is recommended that the pipe material of said steam - cooled wall has to be replaced.
出处 《热力发电》 CAS 北大核心 2010年第1期105-108,112,共5页 Thermal Power Generation
关键词 发电厂 锅炉 包墙过热器 爆管 泄漏 有害元素 回火 脆性 焊缝 熔池深度 thermal power plant boiler steam in weld joint cooled wall harmful element brittleness deep - melting
  • 相关文献

参考文献14

二级参考文献33

共引文献48

同被引文献18

引证文献4

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部