摘要
介绍在杭州湾跨海大桥南引桥滩涂区1430t/50m预制箱梁运架施工中,采用TE1600组合式轮胎走行运梁车,沿双幅桥面将整孔箱梁从桥头运输到前方架桥机的施工技术,以及TE1600轮胎式运梁车的结构组成、关键技术及箱梁运输的相关工艺。
The paper describes the construction technology, which was adopted in the conveyance and erection of 1 430 t/50 m prefabricated box girders in the beach area of the South Approach Spans of Hangzhou Bay Bridge to convey whole-span box girders from an end of the bridge to the bridge girder erection machine in front along two sides using the model TEl600 combined-type tyred girder-transporting vehicle. It also describes-the structural composition of the model TEl600 tyred girder-transporting vehicle, the key technologies used therein, and the process related to box girder conveyance using the vehicle.
出处
《起重运输机械》
2010年第1期8-13,共6页
Hoisting and Conveying Machinery
关键词
运梁车
大型箱梁
运输
施工技术
box girder-transporting vehicle
large-sized whole-span box girder
conveyance
construction technology