摘要
结合核电建设中测量实际情况,以某核电站边角网实测数据为例,对多种模型下的处理结果进行了比较,指出可以优先选用测边网;强调运用Helmert验后方差估计处理测量数据时,取待定点坐标初值尽可能精确,否则会导致迭代求解失效,得不到最终结果.
Considering the practical conditions about the application of surveying control network during nuclear power plant(NPP) construction,with the calculation result of a real triangulateration data comes from the control network of one NPP being built, the paper gives supports on why trilateration should be selected firstly; it also shows given accurate initial coordinates of the unknown points are important and necessary,otherwise the equations can't be iterated continuously and the final result can't be obtained either.
出处
《昆明理工大学学报(理工版)》
北大核心
2009年第6期58-61,共4页
Journal of Kunming University of Science and Technology(Natural Science Edition)
关键词
边角网
Helmert估计
经验定权
核电站
triangulateration
Helmert estimation
experience weighting
nuclear power plant