生产矿的改扩建工程由于生产、改扩建工程的多头掘进作业,互相影响因素多,尤以提升运输的制约,难以组织起快速施工。同煤集团塔山矿利用进回风井临时改绞解决提升运输,以达到改扩建工程的快速施工的目的。
Restricted by hoisting the enlarging construction in a running mine is hard to achieve high speed. In Tashan mine of Datong Coal Group, an air - return shaft is temporaryly reformed into hoisting shaft to speed up the construction greatly.