风险评价模式在HSE管理中的应用 被引量:6

Application of Risk Assessment Model in HSE Management
下载PDF
导出
摘要 根据《中印石油管道项目HSE手册》,对项目进行风险模块划分,以盾构施工模块为例,对其施工过程进行模块综合评价,得到系统安全级数为0.7077,处于中等安全与较安全之间,基本满足要求,为项目的安全环保进行提供了科学依据。 The starting point of HSE management is to prevent the accident. Therefore,early risk identification and risk assessment are the key to HSE management. Through risk analysis and evaluation,we can find the possible impact of HSE and sum up the experience of the past HSE management,and then take the necessary precautionary measures. Combining the 'China-India oil pipeline project HSE Manual' worked out by CNPC Pipeline Bureau,we used fuzzy comprehensive evaluation method to carry on risk assessment of shield construction,safety level is 0.7077,between middle safety and safer level,basically meet the demand.The result can provide a scientific basis for the project's safety and environmental protection.
出处 《油气田环境保护》 CAS 2009年第4期48-50,共3页 Environmental Protection of Oil & Gas Fields
关键词 HSE管理 风险分析 风险评价 风险管理 HSE management risk analysis risk management risk assessment
  • 相关文献

参考文献6

二级参考文献10

共引文献78

同被引文献44

引证文献6

二级引证文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部