分析了TSP203工作原理,介绍了鹅步岭隧道出口右线超前地质预报工作,得出了岩体的工程地质特征,并针对不良地质地段提出了具体建议,以加快工程进度、降低工程风险,从而使施工技术更趋合理。
The TSP203 working mechanism was analyzed,the advanced geological forecast of Ebuling tunnel exit right line was introduced,and the terrene engineering geological characteristics were obtained.The detail suggestions against to defective geological segment were proposed,so as to fasten engineering time and reduce engineering risk,therefore made construction technology more proper.
出处
《山西建筑》
2010年第1期322-323,共2页
Shanxi Architecture
关键词
隧道
超前地质预报
不良地质
施工
tunnel
advanced geological forecast
defective geology
construction