期刊文献+

重庆大剧院大悬挑结构卸载分析 被引量:18

Unloading Analysis for Large Cantilever Structure of Chongqing Grand Theatre
下载PDF
导出
摘要 为了解决大悬挑结构卸载过程中存在的技术难题,采用有限元分析软件ANSYS对重庆大剧院大悬挑结构卸载过程进行了数值模拟分析,根据分析结果确定了拆除临时支撑的合理顺序;采用以变形控制为主、受力控制为辅的双重控制路线,通过与实际施工中的实测值进行对比,确定采用分次、分步的方法进行施工,确保卸载过程中结构的变形和受力始终处于安全范围之内。分析结果表明:该理论模型能较好地模拟大悬挑结构的实际状态。 In order to solve the technical difficulty problems in unloading process of the large cantilever structure, finite element analysis software ANSYS was adopted to simulate the unloading process for large cantilever structure of Chongqing Grand Theatre. According to the analytical results, the reasonable order of temporary supports removal was confirmed, and double-control guideline which regarded the deformation control as the main one and regarded the force control as the secondary one was adopted. Finally, the data measured values in the field were compared with the theoretical results, which determined the use of step-by-step approach in construction and ensured that the deformation and forces of the structure in the unloading process remained in the scope of security. The analytical results show that the theoretical model proposed in the paper can preferably simulate the large cantilever structure.
出处 《建筑科学与工程学报》 CAS 2009年第3期122-126,共5页 Journal of Architecture and Civil Engineering
关键词 重庆大剧院 大悬挑结构 卸载 数值模拟 竖向挠度 Chongqing Grand Theatre large cantilever structure unloading numerical simulation vertical deflection
  • 相关文献

参考文献10

二级参考文献35

共引文献447

同被引文献107

引证文献18

二级引证文献91

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部