摘要
基于北京地下直径线工程DK6+804.1~DK7+060段的施工设计,介绍了CRD工法施工工序,并采用有限元程序软件对CRD工法施工的各步进行模拟计算,并对计算结果进行分析。
The construction procedure of CRD excavation method is introduced based on construction design of DK6 + 804.1 - DK7 + 060 section of Beijing Rail Underground Transit Line Project. Each step of CRD method is numerically simulated by using finite element program and the results are analyzed.
关键词
地下直径线
CRD工法
地表沉降
模拟计算
Beijing rail underground transit line
CRD method
ground settlement
numerical simulation