填沙路堤设计和压实方案及施工控制要点 被引量:3

On the Design and Compacting Plan of Filling Sand Embankment and Its Construction Controlling Key Points
下载PDF
导出
摘要 结合上海长江大桥崇明岛接线工程对填沙路基施工工艺进行了研究。提出了合理的填沙路基结构设计方案、碾压厚度、碾压机械组合以及施工过程控制要点等。研究结果提出沙料外侧1.5m部分采用土工布每0.4m分层包裹加固;每层松铺厚度采用30cm;压实机械采用YZ8JC和YZ14JC;施工中要清表、洒水和推平、碾压。 Combined with Shanghai Yangtze River Bridge project in Chongming Island, the construction technique of road embankment by filling sand has been studied in this paper. Several points have been presented including reasonable embankment structure design plan, rolling compaction thickness, the combination of rolling compaction machine and the construction process monitoring, etc. The results showed four points:1)the outside part of sand about 1.5 m should adopt geotextile to cover and strengthen at every 0.4 m; 2) every loose laying depth should be 30 cm; 3)the rolling compacting machine should adopt YZ8JC and YZ14JC; 4)cleaning the surface, watering, levelling and rolling should be done during the construction.
出处 《中国市政工程》 2009年第5期6-7,共2页 China Municipal Engineering
关键词 路堤 填沙 长江口细沙 压实 施工工艺 road embankment to fill sand fine sand from entrance of Yangtze river to compact construction technique
  • 相关文献

参考文献4

二级参考文献16

共引文献133

同被引文献11

引证文献3

二级引证文献12

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部