摘要
吉林省舒兰市吉舒炮台山水厂扩建工程设计处理能力为1×104m3/d,针对原水冬季低温低浊、夏季暴雨过后偶尔发生高浊、其他时间浊度较低的水质特点,采用了网格反应池、新型气浮/沉淀池、均质滤料气水反冲洗滤池处理工艺。三年多的运行实践表明,该工程运行稳定,处理效果良好,可供类似水厂改造扩建工程参考。
The extended project of Jishu Paotaishan Waterworks in Shulan City has design capacity of 1 × 10^4 m^3/d. Considering the low-temperature and low-turbidity of raw water in winter, the occasional high turbidity water after heavy rain in summer and low turbidity water at other times, the grid reaction tank, new flotation-sedimentation tank and filter with uniform medium and air-water backwashing are employed. The operation for more than three years shows that the project has stable operation and good treatment efficiency, it can provide a reference for reconstruction and extension of similar waterworks.
出处
《中国给水排水》
CAS
CSCD
北大核心
2009年第16期26-28,共3页
China Water & Wastewater
关键词
水厂
扩建工程
新型气浮-沉淀池
工艺特点
waterworks
extended project
new flotation-sedimentation tank
process characteristics