摘要
介绍尼傲加尕水电站厂房布置、稳定计算、设计主要特点及其优化设计情况。设计过程中,深入分析了地形、地质、水文、结构、施工等条件,因地制宜,使厂房的功能性、安全性、经济性等得到很好的统一,电站已安全并网发电2.5 a。可为同类水电站厂房的设计提供一定的参考。
The paper describes the layout, stability calculation, main design features and optimal design of Ni'aojiaduo hydropower station powerhouse. During design, deep analysis of topography, geology, hydrology, structure and construction conditions was made, which well unifies the function, safety and economy of the powerhouse in line with local conditions. The hydropower station has been put into operation in grid for two and a half years, providing reference for design of similar hydropower station powerhouses.
出处
《西北水电》
2009年第3期68-71,共4页
Northwest Hydropower
关键词
厂房
设计
稳定计算
尼傲加尕水电站
powerhouse
design
stability calculation
Ni'aojiaduo hydropower station