摘要
为了完善和推广单代号网络计划技术,利用单代号网络图的基本表示方法,提出赋予工作与其紧后工作之间的逻辑箭线的水平投影坐标长度表示该工作的持续时间的功能及绘制规定,从而给出单代号时间坐标网络图的绘制的方法和步骤。
In order to perfect and spread activity-on-node network planning technique, it is put forward to give the horizontal projection length of logic arrow in an activity with its followed closely ones to present the duration and drawing rules by using basic expressing methods of activity-on-modenet work, thus the drawing methods and program of time-coordinate network of activity-on-node network are given in this article.
出处
《哈尔滨建筑大学学报》
1998年第1期112-115,共4页
Journal of Harbin University of Civil Engineering and Architecture
关键词
单代号时间坐标
网络法
施工组织
建筑
网络计划
activity-on-node time-coordinate net-work plan
generatrix
dummy preceding node
dummy end node