隧道暗挖施工引起的围岩变形分析

Analysis on Ambient Rock Deformation Induced by Hidden-digging Method in Metro
下载PDF
导出
摘要 在复杂的城市地下工程施工过程中,对施工引起的围岩及结构变形进行控制是决定施工成败的关键因素之一。北京铁路枢纽北京站至北京西站地下直径线工程ZJX-2标施工过程中,通过对盖挖法和CRD法各阶段施工引起的围岩及结构变形进行监测,系统分析地层与结构变位及两种施工方法之间的关系,总结出两种施工方法引起的围岩及结构变形规律,对指导施工、控制围岩及结构变形起到很好的作用,使施工始终处于可知可控状态。 It is the critical factor to control deformation in the complex construction process of urban metro. By monitoring the deformation of adjacent rock and structure due to excavation cap method and CRD method construction, the relation between deformation of adjacent rock and structure is analyzed systematically, and the regularity between deformation of adjacent rock and structure and two job practices is summed up. Consequently it is helpful to instruct construction and control deformation of adjacent rock and structure.
作者 汪玉华
出处 《施工技术》 CAS 北大核心 2009年第3期93-96,共4页 Construction Technology
关键词 地下工程 隧道 盖挖法 CRD法 监测 underground engineering tunnel cap method CRD method monitoring
  • 相关文献

参考文献4

  • 1王梦恕著..地下工程浅埋暗挖技术通论[M].合肥:安徽教育出版社,2004:853.
  • 2北京城建集团有限责任公司.GB50299-1999地下铁道工程施工及验收规范[S].北京:中国计划出版社,1999. 被引量:3
  • 3韩瑞庚编著..地下工程新奥法[M].北京:科学出版社,1987:301.
  • 4施仲衡主编..地下铁道设计与施工[M].西安:陕西科学技术出版社,1997:483.

共引文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部