摘要
单机容量2MW级的山西神池风电场大部分施工处于严寒气候条件下。为满足工程质量和进度要求,制定了切实可行的低温混凝土施工技术措施,解决了低温条件下混凝土浇筑成型难等质量技术难题,混凝土质量、强度良好。
Shenchi wind power farm’s unit capacity arrives to 2 MV level.The project is located in cold climate area.According to engineering quality and schedule requirements,the feasible construction technologies of low temperature concrete is established to solve the quality technology question.The concrete’s quality and strength is good.
出处
《施工技术》
CAS
北大核心
2010年第S2期204-205,共2页
Construction Technology
关键词
神池风电场
低温混凝土
塔架基础
施工技术
Shenchi wind power farm
low temperature concrete
tower foundation
construction technology