概述了莱芜矿业有限公司各矿床的水文地质条件、采矿方法沿革,针对矿体不稳固且水大的特点,研发了预控顶上向分段胶结充填采矿法。对该采矿方法采场布置形式、预控顶的施工工艺、落矿方式及有关参数进行了介绍,对适应条件及使用效果进行了评价。
Hydrogeological conditions and the evolution of mining methods of various deposits in Laiwu Mining Co. , Ltd are summarized. Aimed at the characteristics of ore body being unsteady and floodwater, the top pre-control substoping-cementation method was developed. The techniques of top pre-control, manners of ore falling stope arrangement form for this mining method, construction as well as some related parameters are introduced, with their compatible conditions and effect of use evaluated.
出处
《莱钢科技》
2008年第6期41-44,共4页
Laigang Science & Technology
关键词
预控顶
分段
胶结充填
采矿法
top pre-control
sub-section
cementation filling
mining method