浅论下坂地水利枢纽工程引水发电洞洞挖岩爆处理 被引量:4

Discussion on treatment of rock burst during tunneling of power tunnel for Xiabandi Water Control Project
下载PDF
导出
摘要 下坂地水利枢纽地处帕米尔高原,临近地震活动带并处于高地应力区,引水隧洞的最大埋深达1 400 m,高地应力问题较为突出。施工阶段初期即出现了明显的岩爆现象,预计随着开挖深入山体、地应力逐步升高,岩爆问题将越来越突出。结合下坂地引水发电洞工程建设过程中的岩爆预防实际,针对性地提出了措施,对预防岩爆、推动工程进度具有一定的借鉴作用。 Xiabandi Water Control project is located at Pamirs, near an active, seismic zone and within a high geo-stress area; for which the maximum embedded depth of the power tunnel is up to 1 400 m with the problem of high geo-stress. The obvious phenomena of rock burst appeared just during the initial stage of the construction, which is anticipated to be more and more serious along with the tunneling into the mountain body with the gradually rising of the geo-stress concerned. In combination of the actual prevention of the rock burst during the construction of the tunnel, some pertinent countermeasures are put forward herein, which can play a role of reference for the prevention of the rock burst and promote construction progress as well.
出处 《水利水电技术》 CSCD 北大核心 2008年第10期121-123,共3页 Water Resources and Hydropower Engineering
关键词 下坂地水利枢纽 深埋隧洞 高地应力 岩爆预防 Xiabandi Water Control Project embedded depth of power tunnel high geo-stress prevention of rock burst
  • 相关文献

同被引文献16

引证文献4

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部