期刊文献+

竖井横通道转正洞施工方案比选 被引量:19

Comparison of Construction Schemes for Conversion from Horizontal Adit Driving to Main Tunnel Driving
下载PDF
导出
摘要 针对城市地铁竖井横通道转正洞施工难度大、工序繁杂的特点,通过方案比选,提出竖井横通道转正洞采用大包施工工法。该工程现已顺利竣工,工程实践表明,大包法施工安全可靠,技术经济和社会效益显著,可供类似工程参考。 The conversion from horizontal adit driving to main tunnel driving of Metro works has great construction difficulties and complex construction procedures. It is proposed, on basis of construction scheme comparison, that full - envelope construction method should be adopted for the conversion from horizontal adit driving to main tunnel driving. The works has already been successfully completed. The works practice demonstrates that full - envelope construction method can provide safe and reliable construction and significant technical, economical and social benefits. The paper can provide reference for similar works in the future.
作者 李静
出处 《隧道建设》 2008年第4期476-478,共3页 Tunnel Construction
关键词 城市地铁 竖井 横通道转正洞 大包法 Metro vertical shaft conversion from horizontal adit driving to main tunnel driving full -envelope construction method
  • 相关文献

参考文献11

二级参考文献4

共引文献40

同被引文献88

引证文献19

二级引证文献74

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部