摘要 结合110kV变电站的建设,研究了几种装配式结构的设计和建造技术,并指出装配式混凝土柱-钢梁组合结构能够实现全装配化施工。对于装配式结构的预制混凝土柱与现浇基础的连接,采用了新颖的预应力压接式柱脚。简要介绍了装配式110kV齐梁变电站试点工程的情况。 Combining with the construction of 1 lOkV substation, several designs and building technologies of fabricated structure are researched, of which fabricated RCS structure can implement the construction of total assembly. To the connection of precast concrete column and cast-in-place foundation of fabricated structure, prestressed clamped type column bases are applied. The fabricated situation of llOkV Qiliang Substation is introduced brieily.
出处 《施工技术》 CAS 北大核心 2008年第8期96-99,共4页 Construction Technology
关键词 装配式结构 RCS结构 设计与建造技术 预应力压接式柱脚 fabricated structure RCS structure design and construction technology prestressed clamped type column base
  • 相关文献

参考文献4

  • 1M. J. Nigel Priestley. Overview of PRESSS research program[J]. PCI Journal, 1991,36(4) :50-57. 被引量:1
  • 2Jubum Kim. Behavior of hybrid frame under seismic loading [ D ]. Washington: University of Washington,2002. 被引量:1
  • 3Rami A. Hawileh. Computational investigation of the behavior of precast hybrid beam-column connection [ D]. Milwaukee: "fhe University of Wiscomin-Milwaukee,2005. 被引量:1
  • 4唐九如编..钢筋混凝土框架节点抗震[M].南京:东南大学出版社,1989:332.

同被引文献52

引证文献12

二级引证文献29

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部