分析了惠州抽水蓄能电站地下洞室群的施工特点,从层次化、模块化的思路出发,充分利用关键路径技术(CPM)和循环网络仿真技术(CYCLONE)的特点,建立了施工工序模型和整体施工网络模型,并对惠州抽水蓄能电站地下洞室群施工全过程进行了仿真建模.通过将整体施工网络模型与地下洞室群施工组织设计相结合,对惠州抽水蓄能电站地下洞室群施工进行数字仿真,确定了洞室群合理的施工工期,施工进度安排、关键路线与施工强度等.此方法已应用在实际工程中,证明了该建模方法和整体模型的正确性和可行性.
By analyzing the construction characteristics of underground cavern group of Huizhou pumped storage station and taking advantage of critical path method (CMP) network technique as well as complex cyclic operation network (CYCLONE) technique, working procedure models and whole construction network model are created by means of hierarchical and modular method to simulate the overall construction. Through the combination of the established models with construction design of underground cavern group, the digital simulation result is obtained which can consequently determine the time limit for the project, arrangement of the process, key construction route and construction intensity. This method is applied to a practical project, which testifies the correctness and feasibility of this modeling method and overall model.
出处
《昆明理工大学学报(理工版)》
2008年第4期69-73,80,共6页
Journal of Kunming University of Science and Technology(Natural Science Edition)
基金
国家自然科学基金资助项目(项目编号:50479048)
关键词
惠州
抽水蓄能电站
地下洞室群
施工
仿真
Huizhou
pumped storage station
underground cavern group
construction
simulation