摘要 通过对各种类型的高墩柱箱梁现浇支架材料、结构及其特点、适用条件的介绍,对高墩柱混凝土连续箱梁现浇支架的选择进行了综合阐述。并从支架预压和预拱度控制两个方面,对支架施工控制作重点探讨,对桥梁工程具有一定的参考价值。 Based on the introduction to various types of materials and structures as well as the features and applicable conditions of the supports, the selection of the cast-in-situ concrete supports for concrete continuous box girders on high columns is com- prehensively expounded and the discussions focus on the control of the construction of the supports from the aspects of preloading and camber of the supports, providing reference of a certain value for bridge works.
出处 《中国港湾建设》 北大核心 2008年第2期59-61,共3页 China Harbour Engineering
关键词 高墩柱 连续箱梁 现浇支架 施工控制 high column continuous box girder cast-in-situ concrete support constructional control
  • 相关文献

参考文献5

  • 1王文涛主编..刚构-连续组合梁桥[M].北京:人民交通出版社,1995:239.
  • 2刘志辉..刚构-连续梁组合桥力学性能与施工技术研究[D].重庆交通大学,2006:
  • 3林铁民.贝雷片支架变形及沉降的分析[J].福建建设科技,2006(2):41-42. 被引量:5
  • 4JTJ041-2000.公路桥涵施工技术规范[S].[S].,.. 被引量:1725
  • 5范立础..预应力混凝土连续梁桥[M],1988.

共引文献1728

同被引文献16

引证文献3

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部