结合糯扎渡水电站工程概况,建立了环境保护体系,介绍了施工区环境保护的内容,并对施工区环境保护的实施进行了分析,同时采取相应的措施,预防和治理建设项目实施后对环境造成的不良影响,从而使项目区环境状况得到了较大的改善,为电站顺利通过环境保护专项验收奠定了基础。
Combined with the engineering situation of Nuozadu hydropower station, the author builds the system of the environmental protection, introduces the content of the environmental protection in during construction, analyzes the implementation of the environmental protection in the construction area, prevents and controls the harmful effects to the environment after the project construction using the corresponding measures, greatly improves the environmental situation in the project area, lays the foundation for the station smoothly passing the special examination of the environment protection.
出处
《山西建筑》
2008年第14期362-363,共2页
Shanxi Architecture
关键词
水电站
环境保护
污染
施工
规划