针对公司集装箱堆场的堆存能力趋向饱和的现状,为提高场地有效堆存能力,提高场地集装箱周转效率和作业效率,就74库东侧空箱场地改造成龙门吊作业场地方案,进行可行性论证。并提出4种方案,其中选出最佳方案。
In order to enhance effectively the storage capacity, so as to raise the circling efficiency and the operation efficiency, this paper puts forwards a plan which make a feasible proof on reforming the eastern empty container yard of the #74 warehouse into the operation yard against the status that the storage capacity of the container yard is tending saturation. Also this paper puts forward 4 plans, from which it choices one as the optimum.
出处
《港口科技》
2008年第1期23-25,共3页
Port Science & Technology
关键词
龙门吊
堆场
堆存能力
改造
gantry crane yard storage capacity reform