摘要
主要对新奥法监控量测技术在学堂湾隧道中的工程应用进行了介绍,通过对典型断面围岩类别、开挖方法、开挖时间及支护之间关系的分析,初步验证了隧道围岩变形的规律,对该隧道及以后类似工程具有较强的指导意义。
The author introduces in the article engineering application of new austrian tunnelling method in Xuetangwan tunnel.Wall rocks of typical sections,excavation method,excavation time and support are introduced and analyzed in detail in the article,which helps verify wall rock deformation principle and give an guidance in the future similar projects.
出处
《山西建筑》
2007年第33期333-334,共2页
Shanxi Architecture
关键词
隧道
新奥法
监控量测
数据分析
tunnel,new austrian tunnelling method,monitoring and surveying,numerical analysis