移动模架原位现浇简支箱梁施工工艺优化

Construction Technique Optimization of Slide Shuttering to Irrigate Simply Supported Box Girder
下载PDF
导出
摘要 以当前在建的温福铁路原位现浇双线简支箱梁为工程背景,主要介绍了移动模架原位制梁的工艺流程、工艺操作要点,对其优化方案进行了阐述,并指出其与现场制梁的异同之处,值得在今后同类桥梁工程施工中参考与借鉴。 Based on the project of Wen fu railway engineering, in which simply supported double-track box girder being made. This paper introduced the technological process, outline of technological operation and optimization of beam constructing by slide shuttering mainly. Similarities and differences between it and beam fabrication on site is set forth. It may be good for the same kind of bridges to consult and use for reference.
出处 《国外建材科技》 2007年第3期65-67,共3页 Science and Technology of Overseas Building Materials
关键词 移动模架 制梁 工艺 优化 slide shuttering girder construction teehnies optimization
  • 相关文献

参考文献4

  • 1范立础.桥梁工程[M].北京:人民交通出版社,1979. 被引量:10
  • 2铁建设[2005]157号,铁路混凝土结构耐久性设计暂行规定[S]. 被引量:4
  • 3铁建设[2005]160号,铁路混凝土工程施工质量验收补充标准[S]. 被引量:2
  • 4铁科技函[2004]120号,客运专线预应力砼预制梁暂行技术条件[S]. 被引量:1

共引文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部