市中心地带的高层建筑,施工场地狭小,地下室深达十几米,如何支护及开挖,或边开挖边支护,其工序、作业面安排很关键;在开挖中如何排水;如何监测支护变形和周边建筑;以及出现基坑严重渗水、坑涌怎么处理;各种应急措施和技术安全措施等以实例作了介绍。
The high - rise buildings of the downtown area have narrow and limited work areas. The depth of basement is more than ten meters. How to support and excavate? How to drain in the excavation? How to monitor the excavation and surrounding buildings. All kinds of emergency measure and safe technology measure are introduced by examples.