分析了某民房突然倾斜事故的原因,运用锚杆静压桩进行基础加固,对锚杆静压桩加固施工工艺进行了介绍,采用局部断柱顶升法进行纠偏,实践证明该法效果良好,以供其他类似工程参考借鉴。
It analyses the reasons of the declivity happen of one domestic,applies the anchor arm static press pile strengthening the basis,introduces the strengthen construction technology of anchor arm static press pile,adapts the parts cut-off pillar and jacking to correct a error,and practice illustrates that the methods has a good result,can be a reference to the other similar projects.
出处
《山西建筑》
2007年第14期117-119,共3页
Shanxi Architecture
关键词
倾斜
锚杆静压桩
断柱顶升
declivity, anchor arm static press pile, cut-off pillar and jacking