牙塘水库大坝渗流监测分析及安全评价 被引量:7

Seepage Monitoring Analysis and Safety Assessment for Yatang Dam
下载PDF
导出
摘要 牙塘水库主体工程完工后,大坝下游坡脚出现了较大渗水,针对这一现象,利用坝后安全监测设备,进行了2次试蓄水渗流监测,根据监测实测数据,系统分析了大坝渗漏部位危害程度,并作了初步预测及安全评价。 After the main project of Yatang reservoir was finished, much water seepage had appeared on the foot of the dam downstream slope. As for the phenomena, the seepage monitoring was conducted after the first two -times of water impoundment. Based on the monitoring data, the seepage position and harm degree have been thoroughly analyzed, and a preliminary forecast and safety assessment made in the paper.
出处 《长江科学院院报》 CSCD 北大核心 2007年第2期30-33,38,共5页 Journal of Changjiang River Scientific Research Institute
关键词 水库 渗流 量水堰 渗压计 安全监测 reservoir seepage measuring weir osmometer safety monitoring
  • 相关文献

参考文献5

  • 1饶锡保,龚壁卫,刘鸣,等.甘肃省东乡南阳渠灌溉工程牙塘水库枢纽工程蓄水安全鉴定[R].武汉:长江科学院,2005. 被引量:1
  • 2刘嘉火斤,盛金保,彭雪辉.甘肃省东乡南阳渠灌溉工程牙塘水库大坝渗漏机理分析[R].南京:水利部大坝安全管理中心南京水利科学研究院,2005. 被引量:1
  • 3鲍小彦,常江宝,王全武,等.牙塘水库大坝试蓄水观测报告[R].兰州:甘肃省水利水电工程局,2005. 被引量:1
  • 4GB50287-99.水利水电工程地质勘察规范[S].[S].,.. 被引量:120
  • 5SL60-94.土石坝安全监测技术规范[S].[S].,.. 被引量:63

共引文献181

同被引文献40

引证文献7

二级引证文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部