大庆油田高一联污水处理站采用组合式气浮选装置,减少了占地面积及场区工艺管线,提高了出水水质。通过取消一次沉降、污水处理站配电值班室合并到地下水深度处理站配电值班室,降低了工程投资及生产运行费用。运行结果表明,该工程达到了8.0×103m3/d的设计处理能力。
The combined gas floatation equipment is applied to the wastewater treatment in Gaoyilian Station of Daqing Oilfield. It decreases the area occupied and technological pipelines on the spot,and cancels the sedimentation once.The wastewater treatment station is merged with the switch board room of the ground advanced treatment station, so as to reduce the engineering investment and production running cost. Capac water ity of the unit has reached the designed treatment capacity 8.0 × 10^3 m^3/d.
出处
《工业水处理》
CAS
CSCD
北大核心
2007年第2期86-87,共2页
Industrial Water Treatment
关键词
气浮
油田废水
除油
gas floatation
oilfield wastewater
degrease