摘要
莱钢2^#750m^3高炉扩容大修改造,方案制定合理,开炉三天利用系数达到2.4,实现了快速开炉快速达产的目的。
The No. 2 750-m^3 blast furnace in Laigang, through technical modermzation with capacity expansion, realized the set target of sooner starting-up and reaching the set output, with its productivity ratio being 2. 4 three days 'after starting up due to meticulous preparations and a rational starting - up scheme.
出处
《莱钢科技》
2006年第6期18-20,共3页
Laigang Science & Technology
关键词
高炉
开炉
达产
btast furnace
starting-up of furnace
reaching a set output target