摘要
针对太原第一热电厂六期扩建工程安装的两台300MW汽轮机组同时出现凝汽器真空低的问题,分析了引起凝汽器真空低的原因,提出了解决凝汽器真空低问题的措施。
In the light of the problem of the low vacuum of two 300 MW steam turbine units installed in the sixth period extension construction of the NO.1 heat power plant of Taiyuan City occurring at the same time, thfs paper analyzes on the reasons of the low vacuum of the condenser, and advances some measures for solving the low vacuum of the condenser.
出处
《科技情报开发与经济》
2006年第24期312-313,315,共3页
Sci-Tech Information Development & Economy
关键词
凝汽器
真空低
换热效率
填料
condenser
low vacuum
heat exchange efficiency
filling