摘要
通过模拟降雨,对泥土和堆肥细料两种覆盖材料厚度进行实验,得出结论,老港场的覆盖材料可用泥土和堆肥细料,只要覆盖层表面构筑成一定的坡度并压实,日覆盖的厚度可在20cm左右,中间覆盖可在30cm左右,最终覆盖的厚度可在60~100cm之间.
The test work on thickness of two covering materials, clay and fine compost was carriedout through simulated raining. The conclusion was that the clay and fine compost could be used at Lao Gang site. Provided that the covering layer surface formed certain slope and compacted, daily covering thick could be about 20cm or so, the intermediate covering could be about 30cm or-so, and the final covering thickness could be within 60 -100cm.
出处
《环境卫生工程》
1996年第1期7-9,共3页
Environmental Sanitation Engineering